Data Center Electrical Decommissioning | UPS, Switchgear and Generator Removal

Data Center Electrical DecommissioningUPS, Switchgear and Generator Removal

When a data center closes, the servers leave fast. The power infrastructure is what’s left, and that’s what we do. Because we refurbish and resell the equipment, we pay you for gear that other contractors charge to haul away.

Schedule a Walkthrough

Full Electrical Scope

Service entrance to rack whips, quoted as one package

Critical Power

UPS systems and battery rooms, switchgear lineups, and panelboards. The backbone of the facility, removed and purchased.

Standby Generation

Diesel and natural gas generators with automatic transfer switches, from rooftop units to megawatt class machines.

Distribution

PDUs, remote power panels, busway and bus duct, and transformers, pulled and palletized by our own crew.

The Difference

Removal that pays instead of costs

A typical decommissioning bid treats electrical infrastructure as demolition debris. We treat it as inventory. The resale value of the equipment offsets the removal cost, and on well equipped facilities the project nets cash back to the owner. Same building, same deadline, opposite direction on the invoice.

Twin crane lift loading a containerized generator package at the Powerhouse Systems yard

Our crew rigging a containerized generator package onto the lowboy. Recovered equipment is refurbished and resold, which is why we can pay for it.

How We Work

Direct or as your electrical subcontractor

1

Walkthrough

In person or on video. We assess everything from the service entrance to the rack whips.

2

Fixed proposal

One document covering removal scope and equipment purchase value.

3

Insured crew on site

COIs provided, your site safety program followed, your schedule kept. Building owners hire us directly, and ITAD firms, demolition contractors, and GCs subcontract us as the electrical scope.

4

Broom clean handoff

Electrical rooms left broom clean with a documented asset list.

Recent Projects

Data center decommissioning case studies

Every project below was self-performed by our own crew, from disconnect through broom-clean handover.

Nanuet data center decommissioning case study

Nanuet, NY

30,000 sq ft. Eight generators totaling over 11 MW, a 50,000 gallon fuel tank, and forty 30-ton Liebert CRAC units.

Read the case study →

Kansas City data center decommissioning case study

Kansas City, KS

10,000 sq ft taken to bare slab. 750 kW Kohler generator, UPS systems, transfer switches, and the raised floor itself.

Read the case study →

San Diego data center decommissioning case study

San Diego, CA

Two 1,000 kW generators craned out of masonry enclosures, plus Mitsubishi UPS systems and twenty CRAC units.

Read the case study →

Raleigh data center decommissioning case study

Raleigh, NC

8,000 sq ft cleared end to end: two 750 kW Kohler generators, UPS systems, and 2,000 A main service line-ups.

Read the case study →

St. Louis data center decommissioning case study

St. Louis, MO

A 6,000 sq ft data hall with 200 server racks, UPS systems, and switchgear, cleared and turned over.

Read the case study →

Oak Ridge data center decommissioning case study

Oak Ridge, TN

Server racks and standby power removed, with the room turned over as empty, broom-clean space.

Read the case study →

Responsible removal and disposal

Decommissioning is not just hauling things out. We handle the regulated material the right way, and we can document it for your records.

  • Refrigerants are recovered by EPA-certified technicians before any cooling equipment is removed.
  • Transformer oil and fluids are drained and disposed through licensed handlers, with PCB testing where it applies.
  • UPS batteries are sent to licensed recyclers, never to a landfill.
  • Scrap and e-waste are routed to certified recyclers, with disposal documentation available and EPA and DOT transport rules followed.

Common questions

Who is liable during the removal?

Our own insured crew performs the work to your site safety program, and we provide a certificate of insurance before we mobilize.

How long does a decommission take?

It depends on scope, but we move fast and give you a firm timeline in the proposal. Most single-room data center electrical scopes run in days, not weeks.

How do you handle asset accountability?

We work from a documented asset list and leave the room broom-clean, so you have a clear record of what left the building and where it went.

Do we pay you, or do you pay us?

Because we refurbish and resell the equipment, we typically pay you for the lot rather than charging you to remove it. The proposal lays out the numbers in one document.

How fast can you look at it?

Quickly. Call (612) 599-5048, or send photos of your equipment for a same-day ballpark before we even visit.

Have a data center coming offline?

Walk us through it, in person or on video, and we will deliver a fixed proposal covering removal and equipment purchase.

Get a Proposal

Also see: Sell Used Data Center UPS · Sell Used Switchgear

From our blog: The 2026 Decommissioning Wave · Decommissioning Checklist · What Used Switchgear Is Worth

Cart
Enquiry Cart ×
Loading....